Construction Updates

Some Important Dates for You To Know

The following dates are subject to change due to weather conditions and scheduling.

Public Utility Relocation Work 06/06/2016 – 10/13/2016

Demolition (Temporary Local Sidewalk Barricades) 07/12/2016 – 10/07/2016

Excavation / Deep Foundations 10/10/2016 – March 2017

Start Sidewalk / Lane Closures 10/07/2016 – Spring 2018

South Side of Addison & East Side of Clark

  • Clark Street
    • Canopy Over Sidewalk Starts 11/08/2016 – 12/01/2017
    • Lane Closure Will Begin 11/08/2016 – 12/01/2017
  • Addison Street
    • Canopy Over Sidewalk Starts 11/10/2016 – 12/01/2017
    • Lane Closure Will Begin 11/10/2016 – 12/02/2017

Construction 11/07/2016 – 06/30/2018